The Procurement Playbook for Switching Off Polystyrene

Cerda Mycelium Team·

A practical 90-day procurement plan to convert your top three SKUs from EPS foam to mycelium without disrupting fulfillment.

A real plan, not a vision deck

Most "switch off foam" projects die in procurement because nobody writes a real timeline. Here's the 90-day playbook Cerda Mycelium uses with new SMB clients to convert their top three SKUs without disrupting fulfillment.

Days 1–14: Audit and prioritize

  • Pull last 12 months of SKU-level packaging spend
  • Identify the top 3 SKUs by foam volume (not unit count)
  • Document current insert dimensions and drop-test specs

Days 15–30: RFP and sample

  • Issue a sample request to 2–3 mycelium suppliers
  • Specify required certifications (ASTM D6400, TÜV Home Compost)
  • Request per-unit pricing at 500, 2,500, and 10,000 unit tiers
  • Receive samples and run internal drop tests

Days 31–45: Validate

  • Run real shipping trials with 50 units per SKU
  • Measure breakage rate vs. EPS baseline
  • Compare unboxing photos for shelf appeal
  • Calculate EPR fee delta

Days 46–60: Tooling

  • Approve final CAD
  • Issue purchase order for custom molds (5-day Cerda lead time)
  • Lock production schedule

Days 61–90: Phase-in

  • Run mycelium and EPS in parallel for 30 days
  • Monitor fulfillment metrics: breakage, returns, customer complaints
  • Decommission foam supplier contract

Common pitfalls

  • Skipping the parallel run — always overlap suppliers for 30 days
  • Underordering the first mycelium batch — order 20% over your forecast for safety stock
  • Forgetting to update sustainability marketing copy on the product page

Start the 90 days now

Request a sample insert from Cerda Mycelium today. Day 1 of your playbook starts the moment that sample lands on your desk.

Replace foam in your next packaging run.

Free sample inserts grown for your product. Reno-based, ships nationwide.

Request a Sample →